Update PO's In Cost Report

There are times when you have entered POs into Eclipse but when you run the cost report they are nowhere to be found. Use these instructions to update POs in the cost report.


1. In the main menu bar select Control Table  > System Defaults, click the General Ledger tab. 

System Defaults

You can also access this section from Budget Worksheet > Setup Options.

Budget Worksheet

In the Cost Report P.O Totals section make sure the three boxes are ticked

  • Update Cost Report with PO Batch – updates new PO totals from EzyPO and PO Entry Batches.

  • Update Cost Report with PO changes - updates PO changes from editing lines in the PO Maintenance or zeroing POs.

  • Update Cost Report AP/PO Interface –  updates PO changes for POs attached to invoices.

 

2. Click on the Update Cost Report PO Totals / Update CR PO Totals button.  

3. Click Okay and then close the System Defaults window. If unticking in the Budget Worksheet close and re-open the budget worksheet after clicking Update CR PO Totals.

 

Related content

User Security Access and Security Levels
User Security Access and Security Levels
Read with this
Stop PO's From Updating Your Cost Report
Stop PO's From Updating Your Cost Report
More like this
Suppliers
Read with this
Cost Report / Trial Balance
Cost Report / Trial Balance
More like this
Installing Eclipse Software and Login
Installing Eclipse Software and Login
Read with this
PO Actual in Budget Worksheet Does not Match Transactions Tab
PO Actual in Budget Worksheet Does not Match Transactions Tab
More like this